What do submittals typically include in a construction project?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Prepare for the NASCLA General Contractor Exam with our quiz. Use flashcards, multiple-choice questions with helpful explanations to ensure success. Start your exam journey today!

Submittals in a construction project primarily serve the purpose of providing detailed information about the materials, products, and equipment that will be used in the project. These documents ensure that all parties involved in the construction process, including the contractor, architect, and client, agree on the specifications before work begins.

Product specifications include comprehensive details about the materials and products to be employed, such as dimensions, quality standards, and compliance with relevant building codes. This level of detail is crucial for confirming that the proposed elements will meet the project's requirements and adhere to the design intent. Therefore, product specifications are a vital part of the submittal process, ensuring transparency and clarity throughout the construction phase.

In contrast, cost estimates, construction timelines, and site plans serve different functions in project management. Cost estimates relate to budgeting and financial planning, construction timelines focus on scheduling and sequencing tasks, and site plans provide a visual layout of the construction area, which are not typically included in submittals.