What can submittals potentially impact in a construction schedule?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Prepare for the NASCLA General Contractor Exam with our quiz. Use flashcards, multiple-choice questions with helpful explanations to ensure success. Start your exam journey today!

Submittals play a crucial role in the construction process as they involve the submission of various documents, samples, or shop drawings for approval before the actual work can begin. When considering project timelines, submittals can significantly impact the overall project schedules for several reasons.

First, the approval process for submittals often requires time, as architects or engineers need to review and approve the materials, methods, or equipment proposed by the contractor. If submittals are delayed, it can lead to hold-ups in other aspects of the construction process. For instance, if materials are not approved in time, their ordering and delivery can be postponed, which could affect the start of related work.

Moreover, effective project management requires that all phases align correctly within the timeline. If submittals are not completed and approved as scheduled, they can create bottlenecks that extend the duration of the project. This could cascade through various tasks, changing the timeline for other contractors and trades involved in the project.

During project planning, it’s essential to consider how submittal reviews and approvals fit into the overall schedule to ensure that the project stays on track. Thus, while labor costs, material delivery, and design aesthetics are important aspects of construction, the impact of submitt